A CVR (cost value reconciliation) is a report that compares the value a contractor has earned on a contract with the cost it has incurred to the same date, to show the real margin on that job.

Last reviewed
October 7, 2026

A CVR (cost value reconciliation) is a report that compares the value a contractor has earned on a contract with the cost it has incurred to the same date, to show the real margin on that job. Quantity surveyors and commercial managers usually prepare it monthly, and finance uses it to report WIP and profit.

Anyone asking what is a CVR in construction means cost value reconciliation, the report where a quantity surveyor's view of a contract meets the finance team's numbers, and where a job that's losing money usually shows up first. It's the report commercial directors and their QS teams are measured on, and the starting point for WIP and month-end profit.

What does CVR stand for?

CVR stands for cost value reconciliation. Cost is everything the contractor has spent or incurred on the contract up to the cut-off date. Value is what the work done by that date is genuinely worth under the contract. The reconciliation is the step that sets the two side by side at the same date and explains the difference, which is the margin earned so far.

How does a CVR work?

A CVR works by measuring cost and value to one cut-off date, adjusting both so they describe the same work, then comparing the result with the margin the job was priced at. The usual sequence looks like this:

  1. Set the cut-off date. Cost and value must stop at the same point. If they don't, the margin is wrong before anyone looks at it.
  2. Work out the true value. The QS starts from the latest valuation or application for payment, then adjusts for over or under valuation and for variations that haven't been agreed yet.
  3. Work out the true cost. Costs posted to the ledger are the starting point. Accruals are added for work done but not yet invoiced, such as subcontractor work and materials already delivered to site.
  4. Compare and forecast. Value less cost gives margin to date, which is checked against the tender budget. Cost to complete and the forecast final account then give the expected margin when the contract finishes.
  5. Agree and post. Once the commercial director signs the position off, the figures feed WIP and the management accounts.

Is a CVR the same as a valuation?

No. A valuation is the external figure: what the contractor applies to the client for, or what the client certifies. A CVR is an internal report that takes the valuation, corrects it to reflect the work actually done, and puts cost against it.

A contractor can be over valued because it applied for work ahead of progress, or under valued because a variation hasn't been agreed yet. Taking the certified figure at face value hides both, which is why the CVR adjusts value before it's compared with cost.

What is a CVR used for, and who relies on it?

A CVR is the earliest reliable read on whether a contract is making money. When it's accurate and on time, a commercial director sees a package drifting while there's still margin to protect. When it's late, the loss tends to surface at final account, after the money has gone.

WIP and the management accounts both draw on the CVR position, so a weak CVR means the board is reading the wrong numbers.

Many CVRs are rebuilt by hand from spreadsheet exports each month, so they're out of date before the review meeting starts. That gap is what construction cost management software is designed to close.

How does Eque2 handle CVRs?

Eque2 builds CVRs from live cost and value data, so the position in the review meeting is the position on the job. Commitments, applications, valuations and variations sit against the live contract, and the CVR updates as costs move.

In Evision, Eque2's platform for larger contractors, CVRs, valuations, variations and forecasting sit in one live view on Microsoft Dynamics 365 Business Central. CVR check-in and check-out logs every version, so commercial and finance read the same numbers from the same source at the same time.

Hours to minutes

RE:GEN Group's leadership team now generates consolidated CVRs and profit reports in minutes rather than hours with Evision. How RE:GEN Group built group-wide financial visibility

FAQs: CVR

How often should a CVR be done?

Monthly is the usual rhythm, because it lines up with valuations and the month-end close. Contractors often review high-risk or loss-making contracts more often than that. When cost and value data are live, the CVR position can be checked at any point in the month instead of waiting for the next cycle.

Who prepares a CVR?

The quantity surveyor or commercial manager on the contract usually prepares the CVR, because they understand the valuation and the cost to complete. The commercial director reviews and challenges it. The finance team then uses the agreed position for WIP and the management accounts, so both teams need to work from the same figures.

Can you produce a CVR with Sage or Xero?

Sage and Xero handle the core accounts well, but they don't track cost and value by contract, so CVRs usually end up in spreadsheets beside them. Construct adds job costing and CVRs to Sage 50, Sage 200, Sage Intacct or Xero, with commitments and variations held against each job.

About Eque2

Eque2 is the commercial and finance platform for construction, trusted by over 3,000 construction businesses in the UK. Construct brings job costing and contract management to the Sage or Xero accounts a contractor already runs. Evision runs construction commercial and finance management for larger contractors and housebuilders on Microsoft Dynamics 365 Business Central.

Customise a demo!
Built for specialist contractors, Chalkstring delivers accurate, consistent estimating through scalable processes that support long-term business continuity.
SEE IT IN THE SOFTWARE
See how Eque2 handles this
Thirty minutes on your kind of projects, with the reporting your commercial and finance teams actually need.

See the right Eque2 product for your business

Book a demo and we will show you the software on your kind of projects, with the commercial and financial reporting your teams need.